Purpose
Even with active day-ahead and intraday trading, a small surplus or shortage remains on the grid every quarter hour: the perfectly forecast and perfectly traded future simply does not exist. The TSO, the grid operator responsible for the high-voltage grid, must therefore adjust continuously, so that the frequency and the international exchange programmes stay within operational limits. Balancing markets are the organised way in which TSOs reserve and activate flexible capacity for precisely that task.
Division of responsibility
Responsibility is deliberately divided here. Every BRP, a balance responsible party, must keep its own perimeter in balance and limit harmful imbalance as much as possible. The TSO, in Belgium Elia, balances the entire control zone: procures reserves, activates them when needed, and settles the imbalances afterwards. Reserve providers offer capacity and/or energy that meets the technical product requirements set by the TSO. BRP imbalances partly cancel each other out, because one BRP is long, another short; Elia ultimately only covers that net remainder with balancing energy.
Capacity versus activation
Most balancing products are settled in two ways. First, there is a payment for simply standing ready within a contracted time window, expressed per MW, regardless of whether there is actual activation. Second, there is a payment for the energy that is effectively delivered once the TSO activates, expressed per MWh. FCR is mainly about reserved response to frequency. aFRR and mFRR typically combine reservation with activation energy prices. Free bids, uncontracted energy offers, can also compete in the activation merit order without earning a capacity fee for it.
Who can deliver
Large power plants and heavy industry long delivered these services almost exclusively, simply because they were the only ones to reach the required scale. That has since changed: smaller, distributed sources such as batteries, demand response and CHP installations can now take part too, as long as together they exceed the required threshold via prequalification, generally somewhere around 1 MW. Aggregation, often via a virtual power plant, is precisely the mechanism that brings that scale together.
Belgian framing
Elia procures locally, consistent with the European product definitions for FCR, aFRR and mFRR. Cross-border platforms increasingly exchange balancing energy between countries, but prequalification, baselines and the settlement details, the rules of settlement, remain largely TSO-specific. Product parameters, such as auction timing, block structure and volumes, also change regularly. Treat every concrete figure as illustrative, not authoritative, and always verify the current Elia documentation for your own situation.
Link with Smart-E-Grid
Your home battery too can, together with other residential and C&I batteries (batteries at businesses and industry) in a virtual power plant, contribute to FCR, and potentially other products for which the whole is qualified. That stands alongside pure energy market optimisation. Contracted reserve does generally restrict the available state and the schedule of your battery, precisely to guarantee that the contracted capacity is really available at the moment Elia asks for it.
Related articles

Basic principles of the electricity system
Electricity is not stored at scale in the grid: production and consumption must always be in balance. This is how that balance works, and why it is the foundation of every energy market.

European market integration: why our prices are not just Belgian
Belgian electricity prices are partly shaped by French nuclear plants, German wind and Dutch gas prices. This is how European market coupling works, and why it matters for your dynamic contract.

Market liberalisation and unbundling: why you choose your own supplier
Why doesn't the grid operator that owns the cables sell energy any more? Unbundling explains the division of roles behind every energy bill, and why SEG has access to markets without owning any cables.